What's Happening with the Capital's Scaffold-Wrapped Hotel?

Scaffolding surrounding a hotel on a busy street
Scaffolding enveloping the hotel on a central thoroughfare may not be entirely dismantled until 2027.

Along the busiest tourist streets in the centre of Scotland's historic capital stands a monolith of construction framework.

For five years, the establishment on the intersection of the famous Royal Mile and a major bridge has been a covered eyesore.

Visitors find no available accommodations, pedestrians are funneled through tight corridors, and commercial tenants have abandoned the building.

Repair work began in 2020 and was originally estimated to last a short period, but now fed-up residents have been told the structure could persist until 2027.

Further Delays

The main contractor, the primary firm, says it will be "towards the end" of 2026 before the first sections of the frame can be removed.

Edinburgh's council leader a city representative has labeled it a "blight" on the area, while heritage campaigners say the work is "very troublesome".

What is transpiring with this seemingly endless project?

A clean, modern hotel facade without scaffolding
Unwrapped - how the hotel is presented in its intended state on the company's website.

A Problematic Past

The 136-bedroom hotel was built on the site of the old local government offices in 2009.

Projections from when it initially debuted under the a fashion-branded banner, put the development expense at about thirty million pounds.

Remedial efforts got underway shortly after the start of the Covid pandemic with the hotel itself shut for business since 2022.

A section of the street and a significant portion of sidewalk leading up to the intersection of the Royal Mile have been left out of action by the work.

Walkers going to and from the Lawnmarket and Victoria Terrace have been compelled one after another into a confined, sheltered corridor.

A dining establishment a well-known restaurant left the building and transferred to a different location in 2024.

In a comment, its operators said construction activity had compelled them to change the restaurant's facade, adding that "guests were entitled to a superior experience".

It is also hosts restaurant chain a pizza restaurant – which has placed large notices on the scaffold to inform customers it is still open.

The hotel under construction in 2008 Scaffolding going up on the hotel in 2020
Photographs show the the building being built in September 2008 (left) and the scaffolding beginning in 2020 (right).

Slipped Schedules

An update to the council's transport and environment committee in the start of the year indicated that the process of "revealing" the façade would commence in February, with a full removal by the close of the year.

But the contractor has said that is incorrect, referencing "highly complicated" structural challenges for the setback.

"We project starting to dismantle parts of the framework close to the conclusion of the coming year, with further improvements continuing thereafter," they said.

"Efforts are underway closely with everyone involved to ensure we deliver an improved site for the public."

Community and Heritage Concerns

A conservation official, head of heritage body the Cockburn Association, said the work had added to the city's reputation of being "slow" for construction projects.

She said those working on the project had a "public duty" to minimise disruption and should integrate the work into the city's design.

She said: "It causes the walking experience in that area of the city really difficult.

"It is perplexing why there is not some attempt to incorporate it within the urban landscape or develop something more artistic and avant-garde."

People walking through a narrow, covered walkway next to scaffolding
Pedestrians have been obliged to walk down a confined enclosed walkway on a section of the road.

Ongoing Efforts

A company representative said work on "ideas to beautify the site" was continuing.

They continued: "We understand the frustrations felt by the community and businesses.

"This represents a long and drawn-out process, demonstrating the complexity and size of the restoration required, however we are focused on concluding this vital work as soon as is possible."

The official said the local authority would "keep applying pressure" on those involved to wrap up the project.

She said: "This structure has been a problem for years, and I echo the annoyance of residents and local businesses over these continued delays.

"However, I also recognize that the company has a responsibility to make the building secure and that this repair has been hugely complex."

Joseph Aguirre
Joseph Aguirre

A seasoned gaming analyst with over a decade of experience in online casino reviews and strategy development.